5.1 Notes on safety for the first start-up
5.2 Operations before start-up
³ Ensure that the gas supply Company has carried out the supply line vent operations, eliminating air or inert gases from the piping.
³ Slowly open the manual valves situated upstream of the gas train.
³ Adjust the minimum gas pressure switch to the start of the scale.
³ Adjust the maximum gas pressure switch to the end of the scale.
³ Adjust the air pressure switch to the start of the scale.
³ Adjust the pressure switch for the valve leak detection control device (PVP Kit), if present, according to the instructions supplied with the Kit itself.
³ Check the gas supply pressure by connecting a
pressure gauge to the pressure test point 1)(Fig. 27)
of the minimum gas pressure switch: it must be low-
er than the maximum allowed pressure of the gas
train, as shown on the characteristics label.
³ Bleed the air from the piping of the gas train, con-
necting a plastic tube to the pressure test point
1)(Fig. 27) of the minimum gas pressure switch.
Take the vent tube outside the building so you can
notice the smell of gas.
³ Connect two lamps or testers to the two gas line so-
lenoids to check the exact moment at which voltage
is supplied.
This operation is unnecessary if each of the two so-
lenoids is equipped with an indicator light that sig-
nals voltage passing through.
The first start-up of the burner must be carried out
by qualified personnel, as indicated in this manual
and in compliance with the standards and regula-
tions of the laws in force.
Check the correct working of the adjustment, com-
mand and safety devices.
An excessive gas pressure can dam-
age the components of the gas train
and lead to a risk of explosion.
Before starting up the burner, it is good
practice to adjust the gas train so that
ignition takes place in conditions of
maximum safety, i.e. with gas delivery at
the minimum.
WARNING WARNING
Fig. 23
Minimum gas pressure switch
Fig. 24
Maximum gas pressure switch
Fig. 25
Air pressure switch
Fig. 26
Pressure switch PVP Kit
D3854
D3856
D3855
D3855
Fig. 27
D8098
1
DANGER
WARNING
Start-up, calibration and operation of the burner
5
Kommentare zu diesen Handbüchern